Hurricane Maria showed that buildings and solar arrays in Puerto Rico come through a major storm when they are engineered and permitted to the code in force. When they are not, they fail at their weakest connection. Federal engineers who surveyed the island after the 2017 storms documented both outcomes. Their findings matter to anyone planning a commercial or community building there today, especially one meant to keep working on solar panels and batteries when the grid goes down.
In This Article:
What the 2017 storms did to buildings
Two hurricanes hit Puerto Rico in September 2017. Irma’s eye came within 30 miles of Culebra on September 6 while it was a Category 5 storm, and Maria struck as a Category 4 hurricane on September 20. FEMA sent a Mitigation Assessment Team, and its report, FEMA P-2020, puts wind speeds in some areas near or above 145 mph, the design wind speed in the building code of the day. The team singled out two things for severe wind damage: informally constructed buildings, which it defined broadly as those not permitted or not built to current standards, and rooftop equipment that was improperly anchored.
Water did much of the rest. Rain driven by the wind got into many kinds of buildings, critical facilities among them, and the team rated that damage as significant. A frame can survive a storm that still ruins the building’s contents through one lost roof panel or one failed door.
How solar arrays fared
The same report has a chapter on solar installations, and it should reassure anyone who doubts that solar can stand up to a hurricane. At the Puerto Rico Convention Center in San Juan, about 17,000 panels sit on steel structures over the parking areas. Wind speeds there were estimated at 140 mph, yet the team estimated that fewer than 5 percent of the panels were damaged or lost.
A ground-mounted array in Humacao did far worse, and the cause was small. Each panel was held by four clips, and each clip by a single bolt. FEMA’s engineers noted that with no redundancy, one failed clip or bolt would likely let a whole panel lift off, and that a single nut can work loose as wind makes the panels vibrate. Panels and framing that tore free then struck neighboring arrays as wind-borne debris. A third array, built with extra bracing between its posts, showed far less damage, although it also saw lower winds of about 90 mph.
The Department of Energy draws the same conclusion in its guidance on severe weather and solar design, written for federal sites: many of the failures seen in the field come down to fastened joints. It recommends bolting modules through their frames where possible, fasteners that lock against vibration, and bracing against sideways movement. On roofs, it advises against arrays held down by ballast alone and calls for mechanical attachment to the building structure.
The code changed after Maria, and it covers solar
Puerto Rico replaced its building code after the storms. The 2018 Puerto Rico Building Code took effect on November 15, 2018. It follows the 2018 International Building Code and, by FEMA’s account, was the first significant revision since 2011. FEMA counts 316 wind microzone maps in it, covering every municipality, so the design wind speed changes from place to place.
Use matters as much as location: the code’s Table 1604.5 assigns every building one of four risk categories, and each category has its own wind speed maps. An ordinary store or small warehouse is Risk Category II. A hall used mainly for public assembly that holds more than 300 people is Risk Category III. Fire, rescue and police stations and designated hurricane shelters are Risk Category IV, the essential facilities. A community center meant to serve as a shelter and keep its lights on after a storm has to be engineered for that role, so settle the question before design starts.
The code also treats rooftop solar as a structural matter. Section 1603.1.8.1 requires the dead load of a rooftop photovoltaic system, racking included, to be shown on the construction documents. Section 1607.13.5 requires the roof structure to be designed for that load.
Why the building and its equipment should be designed together
A pre-engineered metal building is engineered for a single project and site. Manufacturers that engineer metal buildings in Puerto Rico begin with the wind speed mapped for the site, the exposure of the land around it and the risk category of the building. The main frames, purlins, girts and bracing are sized from those loads, and the drawings carry a professional engineer’s stamp.
Solar belongs in that conversation from the first day. A rooftop array adds weight, and its attachments pass wind uplift into the roof framing, so the engineer needs the array’s layout and loads before the frame is designed. An owner who wants the building to stay open through an outage may also pair solar panels with batteries and a standby generator, and that equipment needs engineered anchorage too.
Two more details shape the frame. Large doors have a weight the engineer must account for. A wall left open, on a loading area or an equipment shelter, changes the design as well, so say early whether it will stay that way.
Salt air works on every connector
Salt in the air corrodes steel and fasteners in every season, storm or no storm. The FEMA team found rooftop connectors that had corroded to failure in under 10 years. One hospital in Arecibo, roughly 0.4 miles from the shore, had considerable corrosion on its rooftop equipment and connectors. The Department of Energy’s guidance calls for watertight NEMA 4X electrical enclosures on solar systems in hurricane-prone areas.
For the building, hot-dip galvanizing is worth asking about. It puts a zinc coating on the main frame and the secondary members, and it is normally offered as an option for sites near the ocean or anywhere salt exposure is expected. Maintenance does the rest: keep the building watertight, wash dirt and mold off the painted panels, and inspect it after every major storm.
A checklist before you build
- Appoint a Puerto Rico-licensed engineer or architect at the start. Someone on the island can confirm which code requirements apply, design the foundation and steer the permit application.
- Find out which office permits the site. The 2018 code names three enforcement authorities: the Permit Management Office (OGPe), the Puerto Rico Planning Board and autonomous municipalities that hold delegated permit powers.
- Put every load on the drawings. That means solar panels and racking, rooftop units and anything hung from the frame.
- Tie the foundation to the frame. The foundation engineer works from the manufacturer’s anchor bolt layout, base details and frame reactions. Misplaced anchor bolts are among the most frequent site problems, so compare them with the layout before any concrete goes in.
- Ask how the panels are fastened. Through-bolted modules, locking fasteners and braced racking are what the federal guidance looks for.
In 2017, the worst building damage followed a missing permit or missing engineering, and the worst solar damage followed a weak fastener. Puerto Rico’s code now asks more of both. A building planned today should be engineered for its municipality and its use, with its energy equipment designed in from the start and its steel protected against the salt air around it.